Mapping & Survey

Metro Phase 3 Corridor Survey

18.4 km of elevated metro alignment mapped through live Bengaluru traffic, delivered as a CAD-ready corridor model with 3 cm horizontal accuracy.

Client
Sunrise Infra Projects
Location
Bengaluru, Karnataka
Duration
6 weeks

The problem

The alignment ran through Marathahalli, Kadubeesanahalli and Bellandur – some of the densest traffic in the country – and the design consultant needed an as-existing corridor model before pier locations could be frozen. A conventional survey party would have needed lane closures on the Outer Ring Road, which the traffic police were never going to approve for a six-week window.

Three quarters of the corridor also fell inside Bengaluru's controlled airspace, under the approach path to HAL and within the Kempegowda green-zone buffer at the northern end.

What we did

Airspace came first. Ananya filed 14 separate Digital Sky permissions covering the corridor in 1.5 km blocks, plus a written coordination protocol with the local ATC for the segments inside controlled airspace. Clearance took 19 days.

Flying was done in the 05:40–07:15 window before traffic built, in 1.2 km segments at 90 m AGL with 80/70% overlap. Kavya's team laid 148 DGPS control points along the corridor overnight, tied to the client's existing benchmark chain, with 31 independent check points held out of processing entirely.

Processing ran in overlapping blocks so a rejected segment could be re-flown the next morning without re-processing the whole corridor.

The outcome

The corridor model came back at 2.8 cm horizontal and 4.1 cm vertical RMSE against the held-out check points. The design consultant used it to shift 11 pier locations before tender, four of which had been sited on top of unrecorded utility crossings that the old drawing set did not show.

No lane was closed at any point during the survey.

“The pier relocation alone saved us more than the survey cost. Having a dated model of what was actually on the ground – not what the 2011 drawing said – changed how the design review ran.”

Rajesh Agarwal, Project Director, Sunrise Infra Projects

What we delivered

  • Corridor orthomosaic at 2.5 cm GSD
  • Digital Terrain Model and 0.25 m contours
  • Classified point cloud, 1.4 billion points
  • Utility and encroachment mark-up layer
  • Accuracy report against 31 independent check points

Similar site?

If your project looks like this one, we can usually quote it from a satellite view and a ten-minute call.

Request a Flight

18.4km

Corridor mapped

2.8cm

Horizontal RMSE

148

DGPS control points

0

Lane closures required

On site at Bengaluru

On site at Bengaluru
On site at Bengaluru
On site at Bengaluru

Ready to get your project in the air?

Tell us the site, the deliverable and the deadline. We will come back with a written scope, a clearance timeline and a fixed price - usually within one working day.

Udrone
Our Services
Contact Us
Mon – Sat 09.00 – 19.00 IST
4th Floor, Sky Vista Tech Park, Kadubeesanahalli, Outer Ring Road, Bengaluru – 560103, Karnataka, India
About Us

Udrone is a DGCA-compliant aerial services company flying survey, inspection and cinematography missions across India. Our certified remote pilots deliver survey-grade maps, 3D models, thermal audits and broadcast-quality film from Bengaluru, Mumbai, Delhi NCR and Hyderabad.

Call WhatsApp Enquire